Hidegkuti Nándor Stadion
Capacity | 5 322 |
---|---|
Country | Hungary |
City | Budapest |
Clubs | MTK |
Category | Design implemented |
Cost | HUF 6.3 mld / bn |
Construction | 2015-2016 |
Design | Bord Építész Stúdió |
Design time | 2014 |
Contractor | ZÁÉV Építőipari, West Hungária Bau |
Advertisement
Hidegkuti Nándor Stadion – design description
The plan for MTK sees the stadium enclosed in outer coat of membrane. Only the east side stands out as three recesses in MTK’s club colour blue will be created to provide a more interesting façade.
The stands with a single tier will be located on three sides of the field with some room for future expansion left in the south. Initial capacity of 5,000-5,500 complies with MTK’s expectations and ticket demand. Despite the club’s rich history, it’s hardly the most popular side in Budapest currently.
The entire stadium will sit atop a large pedestal, which will comprise club offices, commercial outlets and local sports museum, among other facilities.
The project should see groundbreaking in spring 2015 and is expected for delivery by June 30, 2016. It’s budget is initially estimated at HUF 6.5 billion (€21m / $26m).
Advertisement
Renderings
-
2014:
Related news
2017
2016
-
New stadium: Wailing walls and porn in Budapest
Yes, this is a click bait, but a well-deserved one. After all, few stadiums are that controversial before they even open. But from now on, the MTK stadium in Budapest should generate positive emotions!
-
Budapest: MTK stadium opening in 3 weeks
Budapest’s second modern stadium will open its doors on October 13. The timing isn’t perfect, but construction is delivered within the desired timeline.
2015
-
Budapest: Cornerstone mounted at MTK future stadium
As demolition, enabling works and tender ended, construction can finally begin at MTK Budapest future home. But first a simple ceremony was held at the site.
-
Budapest: MTK Stadium ready in mid-2016
Contract signed, now contractors have to get going, because the project has extremely tight time frames. Delivery set for August 31, 2016, while official opening will take place in September.
-
Budapest: New MTK stadium in just 360 days
Less than a year should be enough time to build the brand new Nandor Hidegkuti Stadion in Budapest. Summer of 2016 should bring one more new stadium in Hungary.
-
New construction: The art of demolition in Budapest
Converting destruction into art form isn’t new, but it’s the first time we see stadium demolition illustrated by artistic images. The more interesting it is to see MTK Budapest’s construction site.
-
Hungary: Billions for new stadiums in 2015
They opened three new stadiums in 2014. This year works are to commence or progress at 22 (!) major projects. The government plans to spend 67.144 billion forints.