Stadion Miejski we Wrocławiu
Capacity | 44 416 |
---|---|
Country | Poland |
City | Wrocław |
Clubs | Śląsk |
Category | Design implemented |
Tournament | Euro 2012 |
Cost | 857 mln zł |
Construction | 04.2009 - 09.2011 |
Design | JSK Architekci |
Design time | 2007 |
Contractor | Mostostal Warszawa / Max Boegl |
Within the project | special platform for parking integrated into stadium. |
Notice | Stands will have just one tier making Stadion Miejski the largest one-tiered stadium built orp lanned recently. |
Advertisement
Renderings
pierwotny kształt trybun
Advertisement
Related news
2012
-
Poland: Investor and contractor lawyer-up in Wrocław
First lawsuit has already been filed by German contractors Max Bögl to stop the payment of bank guarantees demanded by Wrocław municipality. But in just a week court battles may start for good – “Gazeta Wyborcza” reports.
-
Poland: Wrocław sacks contractors, demands compensation
Just days after Euro 2012 ended yet another contractor is facing legal action as municipality of Wrocław terminated Max Bögl's contract to build the stadium – Gazeta.pl reads.
-
Poland: Wrocław’s illumination given first test-drive
Though last week investors feared it might not be ready at all for Euro 2012, the system of 700 LED lamps was tested yesterday. Not fully configured yet, but first impression is a rather good one – check for yourselves!
-
Poland: No lights for Euro 2012 games in Wroclaw?
Though it was supposed to be delivered by early April, external illumination of Wroclaw’s Euro 2012 venue will not be ready until end of May. There is also a risk of works being finished after three games of the tournament – “Rzeczpospolita” reads.