Nueva Romareda
Updated: 11.02.2025
Target capacity | 43 110 |
---|---|
Capacity before works | 33 608 |
Country | Spain |
City | Zaragoza |
Clubs | Real Zaragoza |
Category | Construction in progress |
Construction | 2024–2027 |
Cost | €140 M ($145 M) |
Design | IDOM |
Contractor | OHLA, Altuna y Uria |
Advertisement
Nueva Romareda – construction description
The first plans for a new stadium for Real Zaragoza began to emerge as early as the turn of the 20th century, but various political bargains, as well as the financial crisis, thwarted more and more new projects.
The breakthrough came only in connection with Spain's candidacy (along with Portugal and Morocco) to host the 2030 World Cup. Zaragoza decided to seize the opportunity to receive World Cup matches, so another design was created, and after the bid proved victorious, funds were found for its implementation.
The new facility is to be built to replace the old La Romareda stadium. The stadium will be a football-specific facility with a capacity of more than 43,000 spectators, equipped with the latest technology and meeting all conditions for hosting top-level events.
The designers, inspired by the cool northerly winds blowing in the area (the so-called cierzo), have given the rectangular body a bit of dynamism, using subtle convexities and concaves. The building will be covered by a lightweight roof, which will shield not only the entire auditorium, but also the observation deck located at the top.
Construction began in July 2024, but the work is limited in scope until the summer of 2025, involving only the south stand and the demolition of buildings around the stadium. Only after the 2024/25 season Real Zaragoza will move to a temporary stadium, and builders will be given full operational flexibility. The new stadium is expected to be ready in June 2027.
More details about the Nueva Romareda project can be seen on a separate subpage
Advertisement
Pictures
11.02.2025
11.02.2025 © Ayuntamiento de Zaragoza
05.01.2025
05.01.2025 © ObrasRomareda
31.12.2024
31.12.2024 © ObrasRomareda
17.12.2024
17.12.2024 © ObrasRomareda
13.12.2024
13.12.2024 © ObrasRomareda 13.12.2024 © ObrasRomareda
30.11.2024
30.11.2024 © ObrasRomareda
16.11.2024
16.11.2024 © ObrasRomareda 16.11.2024 © ObrasRomareda
06.11.2024
06.11.2024 © ObrasRomareda
24.10.2024
24.10.2024 © Real Zaragoza 24.10.2024 © Real Zaragoza 24.10.2024 © Real Zaragoza
23.10.2024
23.10.2024 © Ayuntamiento de Zaragoza 23.10.2024 © Ayuntamiento de Zaragoza 23.10.2024 © Ayuntamiento de Zaragoza
11.10.2024
11.10.2024 © ObrasRomareda 11.10.2024 © ObrasRomareda 11.10.2024 © ObrasRomareda
05.10.2024
05.10.2024 © ObrasRomareda
21.09.2024
21.09.2024 © ObrasRomareda 21.09.2024 © ObrasRomareda
09.09.2024
09.09.2024 © Real Zaragoza
08.09.2024
08.09.2024 © ObrasRomareda 08.09.2024 © ObrasRomareda 08.09.2024 © ObrasRomareda
05.09.2024
05.09.2024 © ObrasRomareda 05.09.2024 © ObrasRomareda 05.09.2024 © ObrasRomareda
04.09.2024
04.09.2024 © ObrasRomareda 04.09.2024 © ObrasRomareda 04.09.2024 © ObrasRomareda
29.08.2024
29.08.2024 © ObrasRomareda 29.08.2024 © ObrasRomareda 29.08.2024 © ObrasRomareda
27.08.2024
27.08.2024 © Real Zaragoza 27.08.2024 © Real Zaragoza
26.08.2024
26.08.2024 © ObrasRomareda 26.08.2024 © ObrasRomareda 26.08.2024 © ObrasRomareda
25.08.2024
25.08.2024 © Real Zaragoza 25.08.2024 © Real Zaragoza 25.08.2024 © Real Zaragoza
19.08.2024
19.08.2024 © Real Zaragoza 19.08.2024 © Real Zaragoza 19.08.2024 © Real Zaragoza
18.08.2024
18.08.2024 © ObrasRomareda
13.08.2024
13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza 13.08.2024 © Real Zaragoza
09.08.2024
09.08.2024 © ObrasRomareda 09.08.2024 © ObrasRomareda
07.08.2024
07.08.2024 © Ayuntamiento de Zaragoza 07.08.2024 © Ayuntamiento de Zaragoza 07.08.2024 © Real Zaragoza
06.08.2024
06.08.2024 © Real Zaragoza 06.08.2024 © Real Zaragoza 06.08.2024 © Real Zaragoza 06.08.2024 © Real Zaragoza 06.08.2024 © Real Zaragoza
05.08.2024
05.08.2024 © ObrasRomareda 05.08.2024 © ObrasRomareda 05.08.2024 © ObrasRomareda
30.07.2024
30.07.2024 © Real Zaragoza 30.07.2024 © Real Zaragoza
28.07.2024
28.07.2024 © ObrasRomareda
25.07.2024
25.07.2024 © ObrasRomareda 25.07.2024 © ObrasRomareda
23.07.2024
23.07.2024 © ObrasRomareda 23.07.2024 © ObrasRomareda
22.07.2024
22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza 22.07.2024 © Real Zaragoza
20.07.2024
20.07.2024 © ObrasRomareda
19.07.2024
19.07.2024 © ObrasRomareda 19.07.2024 © ObrasRomareda 19.07.2024 © ObrasRomareda
16.07.2024
16.07.2024 © ObrasRomareda 16.07.2024 © ObrasRomareda
14.07.2024
14.07.2024 © ObrasRomareda
Related news
2025
-
Spain: The second phase of Nueva Romareda construction is about to begin, new tenders launched
The Board of Directors of La Nueva Romareda SL has approved the next stage of construction for the new stadium, as well as the services and supplies for the temporary venue at Parking Norte de la Expo, where work is already in progress.
-
Spain: Second phase of Nueva Romareda construction approved
The second phase of works at the La Romareda stadium has received all the necessary permits. The construction is set to begin in February, starting with the building of the structure for the new Gol Sur stand.
-
Spain: Work begins on temporary stadium for Real Zaragoza
The urbanisation work to build a portable stadium for Real Zaragoza is fast approaching. The first activities on the construction site are scheduled for this coming Monday, 20 January.
2024
-
Spain: Modular stadium construction in Zaragoza will begin in early January
Two parking lots, a fan zone, picnic areas, and flood protection—this is how the surroundings of the temporary football stadium at Parking Nord will look, where Real Zaragoza will play for the next two seasons.
-
Spain: Construction of Nueva Romareda will take three months less than expected
IDOM, the company responsible for the design, is revealing more and more details about the future stadium in Zaragoza.
-
Spain: Construction of Nueva Romareda turns out more expensive than expected
The construction of the Nueva Romareda stadium is set to cost more than initially projected, with an additional €72 million needed from two of the three partners of the La Nueva Romareda SL group to keep the project on track.
-
Spain: Four companies interested in construction of Nueva Romareda
Four companies are competing for the continuation of the demolition works of La Romareda and the construction of the new stadium. The board of directors of La Nueva Romareda has approved the proposal for the contracting table. We also know the final deadline for submitting bids for the tender.
-
Spain: Wave of stadium upgrades sweeps through the Iberian Peninsula
In recent years, work on Spanish stadiums has not stopped, and the 2030 World Cup has provided another important impetus for the renovation of facilities. With work on the Bernabéu, Camp Nou and Balaídos already underway, 9 La Liga venues are awaiting their turn. Rosaleda, Romareda, Riazor and La Cartuja join the group as 2030 World Cup hosts.
-
Spain: First renderings of Real Zaragoza's temporary stadium
MLN Group, in a joint venture with Nussli Iberia, which won the tender for the construction of Real Zaragoza's temporary stadium, has revealed the first visualizations of the facility. The stadium will be operational for the 2025/2026 and 2026/2027 seasons.
-
Spain: La Romareda to disappear by mid-October 2025
October 2025. That’s the time when all Zaragoza fans will say goodbye forever to their beloved La Romareda and welcome their new stadium. The company responsible for demolition and construction must ensure that no trace of the current football stadium remains no later than one year after it closes.
-
Spain: Tender announced for next phase of Nueva Romareda construction
Nueva Romareda has announced a tender for €138.5 million for a major phase involving the demolition of the current facility and the construction of a new stadium. The public tender will determine the works for Phase 1B.
-
Spain: Two companies interested in building temporary stadium for Real Zaragoza
On September 12, the deadline for submitting bids for the construction of a temporary football pitch for Real Zaragoza at the North Parking lot expired. This temporary facility will be used during the work on La Romareda.
-
Spain: 'Zaragoza never gives up' banner will cover works at La Romareda
The demolition of La Romareda is progressing at a rapid pace. The work is currently focused on removing the structure of the old El Cubo building, and it is estimated that all surface work will be completed in the coming days. Underground work is set to begin in the second week of September.
-
Spain: Real Zaragoza prepares for construction of modular stadium
La Nueva Romareda SL, a company formed by the Aragon government, the City Council, and Real Zaragoza, is adhering to the timeline for the construction of the modular stadium at Parking Norte to ensure its readiness for the 2025/2026 season.
-
Spain: Work underway at La Romareda. Another stadium with eco-friendly building certification
While specialized machines gradually erase elements of the old Real Zaragoza stadium, the city is already considering how the new Romareda will look in the future. An important tender is expected to be announced soon. However, what do we know so far?
-
Spain: Demolition work underway at La Romareda. Temporary stadium to be built
On July 7, the day after Enrique Bunbury's concert, demolition work began at La Romareda. The completion of this project is scheduled for the end of 2027 or the beginning of 2028. In the upcoming season, Real Zaragoza will continue to play at the venue, with Gol Sur being the first section to be demolished.