Arena Zabrze (Stadion Górnika Zabrze)
Updated: 14.12.2024
Target capacity | 31 871 |
---|---|
Capacity before works | 3 000 |
Country | Poland |
City | Zabrze |
Clubs | Górnik Zabrze |
Category | Construction in progress |
Construction | 09/2011 – 06/2016 (phase 1), 06/2023 – 2025 (phase 2) |
Cost | PLN 192,5 M (phase 1), PLN 46 M (phase 2) |
Design | Joint venture with GMT Ltd as leader/ |
Contractor | Polimex-Mostostal (phase 1), Mostostal Zabrze (phase 2) |
Advertisement
Arena Zabrze – construction description
When was the construction permit for the stadium in Zabrze obtained?
In order to redevelop the stadium, in late 2007 the City of Zabrze set up a company called Stadion w Zabrzu (Stadium in Zabrze). In 2008, an architectural concept was selected, and in 2009 the construction design was commissioned. On 23rd April 2010, the company received preliminary design documentation, and on 15th July 2010 it applied for a construction permit, which it obtained on 19th November 2010.
What was the first phase of rebuilding the Górnik Zabrze stadium?
On 15th March 2011 a tender was announced for the first stage of the project, including the reconstruction of the north, east and south stands. Polimex-Mostostal was selected as the main contractor and committed to carry out the project for more than PLN 192.5 million (it was the only bid which did not exceed the budget allocated for the task, which amounted to less than PLN 199 million). The construction contract was signed on 24th August 2011, and the works were to be completed in April 2013.
Why was the initial agreement with the first contractor for the stadium in Zabrze terminated?
On 8th September 2011 the construction site was handed over to the contractor. On 14th September the foundation act was solemnly signed in the company of, among others, representatives of the club, city authorities, sponsors, designers and contractors, as well as former Górnik Zabrze stars and fans. However, Polimex-Mostostal ran into trouble over time and had problems with the planned finishing of the investment. The completion date was pushed back to November 2013, and when this too was not met, the Stadion w Zabrzu company decided to remove the contractor from the task.
What did the redevelopment of Zabrze stadium look like after the contract with the developer was terminated?
After Polimex-Mostostal left the construction site, the Stadion w Zabrzu company carried out an evaluation and decided to take over the responsibility for completing the works, starting in March 2014 by issuing tenders for individual stages of further works. However, the construction was significantly prolonged in time compared to the original assumptions.
Throughout the redevelopment, the stadium remained in use and Górnik Zabrze continued to play its Ekstraklasa matches there. New, temporary lighting masts were erected to replace the demolished ones, which stood just outside the corners of the field. The capacity of the stadium was significantly reduced to around 3,000 spectators who were seated in the (only undemolished) main stand on the west side, completed in autumn 1935 (a year after the stadium opened). In August 2015 additional seats were made available to fans on the lower tier of the new stand behind the south gate, and in October 2015 similar spaces on the opposite side.
On 21st February 2016, the new stands were made fully accessible to fans for the first time, and the Great Derby of Silesia between Górnik and Ruch Chorzów (0:2) was attended by a sold-out crowd of 24,563 spectators. Work on the completion of the first phase of construction continued until June 2016. After the opening of the new auditorium, the old west stand was used by journalists covering the on-field action. As part of phase one, an entrance walkway was also constructed on the eastern side, along with an underground car park beneath it.
When will the fourth stand be built in Zabrze?
The realisation of the first phase of the project came at the cost of a major organisational and financial effort. After its completion, it was clear that the construction of the fourth stand, which would fill the gap and turn the facility into a closed, coherent architectural block, would not start immediately. The main obstacle was, of course, financial.
The first step on the way to completing the construction was the demolition of the old main stand. To make it possible, its infrastructure first had to be moved to the new part of the stadium. In 2018, new changing rooms, press areas, a gym, regeneration rooms, coaches' rooms and other function rooms were completed in the south-west corner. The final element was the television infrastructure, which was moved to the east stand in early 2023.
The key decisions on the way to the construction of the fourth stand were made in 2022. On August 22, 2022, the city signed an agreement with Pekao S.A. bank to handle and guarantee a bond issue that would provide financing for the investment.
The tender for the construction of the fourth stand was called at the beginning of March 2023. At the same time, the demolition of the old main stand also started, which was carried out by AKPE Group. The tender for the construction was won by Mostostal Zabrze, which offered a sum of just under PLN 46 million. The contract with the contractor was signed on June 19, 2023. Work was already underway at the end of June 2023. The fourth stand should be ready for use in spring 2025.
Advertisement
Pictures
-
14.12.2024
12.12.2024
23.11.2024
05.10.2024
21.09.2024
23.08.2024
09.08.2024
23.07.2024
14.07.2024
12.07.2024
27.06.2024
21.06.2024
13.06.2024
28.05.2024
11.05.2024
27.04.2024
11.04.2024
09.04.2024
03.04.2024
29.03.2024
15.03.2024
09.03.2024
08.03.2024
07.03.2024
06.03.2024
05.03.2024
04.03.2024
01.03.2024
20.02.2024
16.02.2024
13.02.2024
01.02.2024
03.01.2024
18.12.2023
14.12.2023
01.12.2023
28.11.2023
13.11.2023
24.10.2023
13.10.2023
02.10.2023
22.09.2023
18.09.2023
08.09.2023
22.08.2023
18.08.2023
25.07.2023
24.07.2023
20.07.2023
05.07.2023
20.06.2023
16.05.2023
19.04.2023
18.04.2023
17.04.2023
14.04.2023
13.04.2023
06.04.2023
04.03.2023
06.06.2016
26.04.2016
18.03.2016
14.01.2016
15.12.2015
13.11.2015
27.10.2015
27.09.2015
23.09.2015
08.08.2015
23.07.2015
15.06.2015
01.06.2015
29.04.2015
13.03.2015
08.12.2014
26.09.2014
03.09.2014
30.07.2014
12.09.2013
23.08.2013
31.07.2013
11.07.2013
13.06.2013
14.05.2013
23.04.2013
11.04.2013
27.02.2013
08.02.2013
08.01.2013
18.12.2012
27.11.2012
06.11.2012
22.10.2012
12.10.2012
27.09.2012
05.09.2012
20.08.2012
06.08.2012
17.07.2012
22.06.2012
29.05.2012
13.05.2012
11.04.2012
11.04.2012
19.03.2012
03.03.2012
29.02.2012
10.02.2012
12.01.2012
30.12.2011
15.12.2011
07.11.2011
20.10.2011
30.09.2011
14.09.2011
Related news
2017
2016
-
New stadium: From Adolf Hitler to Arena Zabrze
Nazi references work well in politics, so why not at StadiumDB? Especially when they’re so well deserved. After all, Adolf Hitler was this stadium’s first name-holder!
-
Poland: Last-minute challenge for Zabrze
Countdown begins, but opening of the newly-renamed Arena Zabrze isn’t certain just yet. 400 workers are on site daily to make sure Poland’s most honoured derby takes place!
2015
-
Poland: Stadium in Zabrze changes name
Starting next year, the new stadium in Zabrze will be called Arena Zabrze. This simple changed is considered a prelude to the venue’s first naming rights deal.
-
Poland: Torcida in bloom for Górnik Zabrze
After over two years of waiting fanatic supporters of Górnik Zabrze can now see their stadium flourish… with seats. All in the hope of saving Górnik’s license for upcoming season.
-
Poland: Fight against time in Zabrze
Last spring it was hoped the new stadium of 14-time champions Górnik Zabrze will be opened by early 2015. Now in 2015, it will be good if one stand gets opened before year ends….
2014
-
Poland: Construction resumes in Zabrze
The city today handed over Stadion Ernesta Pohla’s construction site to new contractors. Work already got under way to deliver the roof within 3 months. More progress is expected soon.
-
Poland: New stadium in Zabrze delayed further
Three stands for over 24,000 people were supposed to open for fans of Poland’s most successful team in April… last year. But they’re still not ready and the municipality just admitted they have no money to finish works.
-
Poland: Two projects (re)launched in Łódź and Zabrze
This week brought major developments regarding two new stadiums in Poland. Construction is expected to restart in Zabrze, while contractor should soon be known for Widzew Łódź new ground.
2013
-
Poland: Zabrze drop contractor, work further delayed
Situation is heating up at the largest ongoing stadium construction in Poland. Three stands to hold over 24,000 people in Zabrze may have even one year more to open as the municipality sacked general contractor over insufficient pace.
-
Poland: Uncertainty over Zabrze new stadium
It’s exactly 41 days before deadline for delivery of three new stands in Zabrze, accommodating over 24,000 people. But current Ekstraklasa leader Górnik may have to plan opening for late next year, because general contractor is on the brink of insolvency and works aren’t progressing at all.
-
Poland: Zabrze stadium delayed once more
First three stands of the new 32,000-seater in Zabrze were to be delivered in just several days. But it's been known for months that it's not possible. Now it gets worse, as even the new September deadline isn't within contractors' reach.
2012
-
Naming rights: One more deal for Allianz?
Insurance giant already bought rights for three stadiums in Germany, France and Australia. Will Poland deliver their fourth arena? Municipality of Zabrze hope so as they negotiate with Allianz, Sport.pl writes.
-
Poland: Works slowdown in Zabrze raise concerns
Financial difficulties of the general contractor caused delays in Zabrze, where Polimex-Mostostal is building the new 32,000-seater stadium. Investors are very concerned over abilities of the company to finish works in time.