Target capacity 22 087
Capacity before works 15 034
Country Germany
City Kiel
Clubs Holstein Kiel
Category Construction in progress
Cost €75 M ($87.7 M)
Construction 2026–2030
Design HPP Architekten, AX5 architekten
Contractor Zech Sports GmbH

Advertisement

Holstein-Stadion – construction description

Although three stands at Holstein-Stadion have already been rebuilt since the beginning of the 21st century, these changes were mostly temporary and did not meet the ambitions of the club or the city (though they did allow the minimum licensing requirements to be met).

Following years of effort, and thanks to the cooperation of the state (Land) and city authorities, the club, and private investors, a project has finally been developed that lives up to the ambitions of the state capital and a team aiming for the Bundesliga.

The plan envisages a complete redevelopment of the stadium, carried out in stages between 2026 and 2030. The first phase began after the end of the 2025/26 season and will run until March 2028. It includes the construction of a new main stand on the northern side (opposite the existing one).

Once completed, the stadium will be a modern football venue with a capacity of over 22,000 spectators, of which 44% will be standing areas. The ribbed roof structure is inspired by shipbuilding, while the distinctive “cut-off” corners will give the stadium a recognizable and unique shape.

Further details on the Holstein-Stadion redevelopment project can be found on a dedicated subpage