Continental-Arena
Updated: 30.06.2015
Capacity | 15 115 |
---|---|
Country | Germany |
City | Regensburg |
Clubs | Jahn Regensburg |
Category | Construction completed |
Construction | 2014-2015 |
Cost | € 52.7 million |
Design | agn Niederberghaus & Partner |
Contractor | BAM Sports |
Advertisement
Continental-Arena – construction description
Building a new stadium for Jahn has been on the table for a few years, but it wasn't until September 2013 that contractor was finally selected and approved, seeing the planning application filed in late November.
Should it be approved without problems, work may start in February with BAM moving to the site in southern outskirt of Oberisling already in January. From that moment the company will have 18 months exactly to deliver the stadium, suggesting late 2015 as opening date.
The design is thought to mimic classic English stadiums with four independent stands, each with distinctive red cover that also forms part of the façade cladding and is the stadium's most distinctive feature. Stands put close to the pitch are to have 21 rows on each side with no floodlight masts in corners to enable future expansion. Instead, there are to be 28 small masts atop the roof.
Capacity would initially be set at 15,000 with 18,000 maximum if the corners are filled eventually. Of that size 6,000 people will be standing, mostly (5,250) in the southern fanatic stand and also in the away section (750), north. Western main grandstand is to have 960 business seats with over 1,000 sqm of hospitality space behind it.
The stadium will easily be accessible from the city's southern bypass and will offer some 2,500 parking spaces. Overall cost was initially planned to stay below €30 million, but has grown to €52.7 million.
Advertisement
Pictures
-
30.06.2015
31.05.2015
29.04.2015
27.03.2015
26.02.2015
13.01.2015
13.12.2014
11.11.2014
07.10.2014
29.08.2014
21.07.2014
30.06.2014
18.06.2014
23.05.2014
17.03.2014
05.03.2014
12.02.2014
Related news
2016
2015
-
New stadium: A long opening in Regensburg
Today marked nearly two weeks since opening events began at Continental Arena. As this marathon ends, the only sad point is that it’s only a 4th league stadium.
-
Germany: No agreement on revenue share at Continental Arena
Less than half a year before stadium opening there’s still no agreement between the city of Regensburg and SSV Jahn. Negotiations have been ongoing for months, but revenue share is still unclear.
2014
-
Regensburg: Continental Arena topped, but attendance fears arise
Yesterday saw the topping out ceremony of Continental Arena in Regensburg. The stadium’s primary roof structure is ready and now the question is… who will go to games at the new stadium?
-
Germany: Regensburg new arena sponsored by Continental
Renowned tire manufacturer Continental acquired 5-year naming rights for the new stadium under construction in Regensburg. Local club Jahn won’t benefit from the deal, though.