Giresun Çotanak Stadyumu

Updated: 04.12.2020

Capacity 22 028
Country Turkey
City Giresun
Clubs Giresunspor
Category Construction completed
Construction 11/11/2016 - 15/10/2020
Cost TRY 153 million
Design Bora Soykut, Azaksu Mimarlik
Contractor Siyahkalem Mühendislik İnşaat

Advertisement

Giresun Çotanak Stadyumu – construction description

The idea of building a new stadium on Giresun's east end was born in 2013, as part of the nationwide programme of building new football venues. The city is famous for cherries and nuts, with hazelnut present both in Giresun's coat of arms and Giresunspor's crest. Thus, the stadium's name is also that of Giresunspor – Çotanak (husked hazelnut) Arena.

The name became subject to controversy more than once, interestingly. A year into construction, in 2017, a dictate by Recep Tayyip Erdoğan ordered all stadia named 'arena' to change their name to stadı/stadyumu. Çotanak Stadyumu would do, however local community and authorities have requested for the stadium to have its name transferred from the city's old ground, the Atatürk stadium. Final name is to be established after opening.

While Giresun as a city has passed 100,000 inhabitants narrowly, the stadium's capacity was set at a generous 22,000+ level. Along with the football venue, an indoor swimming pool with 1,200 seats was planned, a training field with running track and room for up to 40 retail outlets hidden within a vast elevated concourse. All this, combined with significant parking, occupied over 113,000 m2.

The stadium's volume may be seen as impressive. It looks bigger than it actually is, especially with the auditorium spread across two vast tiers and with a spacious atrium behind the stands, protecting the public concourse from quite frequent rain. In total, the stadium is covered by 25,000 m2 of PVC and ETFE membranes.

Design work was commissioned from a renowned Turkish practice, Azaksu. Both the stadium and natatorium have elliptical form and natural colours, mimicking the hills surrounding them. The stadium also has tall arcades, ensuring proper ventilation of the concourse area.

The stands have two tiers along both sides but a single one on each end, topped by glazed floor spaces. A small strip of skyboxes was also created between the two levels, offering 49 boxes.

Construction officially began in November 2016 and was initially hoped to end by the end of 2017. This immediately proved too optimistic. During the first year the project reached 50% and then began to slow down painfully. By mid-2018 it was only at 70%, reaching 90% only around the end of 2019. In 2020 the COVID-19 pandemic was blamed for further delays, though it's clear the project was troubled long before.

The deadline for delivery was changed numerous time with very little explanation, even in 2020 being changed several times. Because of the number of changes we cannot confirm the price tag of TRY 153 million as final (upon groundbreaking in 2016 it was equal to €45.7m).

Advertisement

Pictures

21.10.2020

24.09.2020

08.08.2020

29.07.2020

22.12.2019

19.06.2019

26.11.2018

30.08.2018

17.07.2018

03.03.2018

05.10.2017

30.07.2017

30.05.2017

27.02.2017

Related news

2021

2020