Stadion Miejski w Nowym Sączu (Stadion Sandecji)
Updated: 24.09.2024
Target capacity | 8 111 |
---|---|
Capacity before works | 2 988 |
Country | Poland |
City | Nowy Sącz |
Clubs | Sandecja |
Category | Construction in progress |
Construction | 2021–2024 |
Cost | PLN 100 million ($25 million) |
Design | Anna i Bartosz Michalscy |
Contractor | Grupa Blackbird |
Advertisement
Stadion Sandecji – construction description
Construction of a new stadium in Nowy Sącz was expected to begin back in 2017, when Sandecja won promotion to the Ekstraklasa. A venue for 8,000 to 10,000 people was envisioned by the then-mayor Ryszard Nowak but his vision quickly proved impossible to carry out, especially in such optimistic time frame.
The concept’s price tag quickly grew from PLN 20 million to 50, then to over 100 million, more than the city was able to finance. That’s why new mayor Lubomir Handzel commissioned a scaled down plan to only meet minimum Ekstraklasa minimum of 4,500 seats, including under-soil heating and modern facilities. But spaces behind goals were to be left for further expansion to the desired 8,000+.
After several delays the design+build contract was signed in mid-2021. Grupa Blackbird, a joint venture of engineering and construction companies, promised to deliver the initial stadium for PLN 50.7 million, under budget. Work began immediately with the demolition of the north stand and creation of a new playing field. Work is phased to enable constant use of the stadium.
Advertisement
Pictures
-
24.09.2024
21.05.2024
23.04.2024
03.03.2024
30.10.2023
13.10.2023
01.10.2023
02.08.2023
03.07.2023
13.06.2023
14.05.2023
05.05.2023
13.04.2023
30.03.2023
08.03.2023
24.02.2023
01.02.2023
14.01.2023
01.01.2023
20.11.2022
07.10.2022
28.08.2022
12.08.2022
14.07.2022
24.06.2022
23.06.2022
20.06.2022
28.05.2022
25.04.2022
13.03.2022
16.02.2022
21.10.2021
09.09.2021
18.08.2021
Related news
2024
-
Poland: Stadium construction in Nowy Sącz delayed another year?! New damages reported!
When it seemed that the construction of the new stadium for Sandecja was finally nearing a happy conclusion, a series of obstacles have emerged in recent weeks. These could lead to further delays, and the promise of city president Ludomir Handzel regarding the completion date of the investment may not be fulfilled. Why?
-
Poland: We Know the Opening Date of stadium in Nowy Sącz
A tender has been announced for the completion and realization of the municipal stadium in Nowy Sącz on Kilińskiego Street. The deadline for submitting offers is May 28, with construction scheduled to be completed by December 27 of this year. However, there is a chance that Sandecja will play at the new facility as early as autumn.
-
Poland: Last year of Sandecja Stadium construction. Who is the author of the project?
The construction of the new Sandecja stadium is taking longer than anyone could have predicted. Finally, however, after many months of various disruptions, it seems that the investment is heading towards a happy ending. According to information recently provided by the city authorities, the facility will be ready later this year.