Skovens Arena

Updated: 15.09.2025

Target capacity 24 000
Capacity before works 19 433
Country Denmark
City Aarhus
Clubs AGF
Category Construction in progress
Cost DKK 994.6 M ($140 M)
Construction 2024–2027
Design Zaha Hadid Architects, Sweco Denmark, Tredje Natur
Contractor A. Enggaard A/S

Advertisement

Skovens Arena – construction description

The construction of a modern football arena in Aarhus, Denmark’s second-largest city, was made possible by a private donation which, even after a significant increase in costs, still covers more than half of the funds required for the project.

The plan calls for the demolition of the over 100-year-old Aarhus Stadion (known as Ceres Park since 2015) and the construction of an entirely new venue on the same site. Renowned architectural studios from around the world competed to design the stadium, with the winning concept created by the British firm Zaha Hadid Architects in cooperation with local partners Sweco and Tredje Natur.

The project is inspired by the forested surroundings of the stadium. Its distinctive feature will be a unique façade composed of tilted reinforced-concrete columns combined with decorative wooden slats. The redevelopment will preserve two sports halls from the old stadium, which used to adjoin the main stand.

Preliminary work related to the project began in November 2023. In early 2024 the main stand was demolished, followed by the remaining structures the next year. Since then, AGF has been playing its matches at a temporary stadium. Completion of the new venue is scheduled for March 2027.

More details about the Skovens Arena project can be found on a separate subpage

Advertisement

Pictures

27.08.2025

04.08.2025

30.06.2025

31.05.2025

25.04.2025

28.03.2025

10.03.2025

28.01.2025

02.01.2025

27.11.2024

30.10.2024

30.09.2024

28.08.2024

24.07.2024

01.07.2024

02.06.2024

01.05.2024

27.03.2024

03.02.2024

06.11.2023