Estadio La Cartuja
Updated: 21.02.2025
Target capacity | 75 000 |
---|---|
Capacity before works | 57 619 |
Country | Spain |
City | Seville |
Clubs | – |
Category | Construction in progress |
Cost | €15 M ($15.7 M) |
Construction | 07/2024 – 03/2025 |
Advertisement
Estadio La Cartuja – construction description
The reconstruction of Estadio La Cartuja is primarily aimed at eliminating the athletics track, lowering the pitch, and bringing the stands closer to the playing field by building additional lower parts of the auditorium.
The stadium will thus gain a football-specific character, and its capacity will increase to 70,000 spectators (together with boxes, press seats, etc., it will total 75,000), making it one of the largest in the country.
Plans to rebuild the stadium came about after Spain was announced as co-host of the 2030 World Cup (Estadio La Cartuja is to be one of the venues for the tournament). Although the modernization will quite significantly change the look of the facility, its cost is surprisingly low (€15 million).
Construction work began in July 2024 and is expected to last until the end of March 2025, so that the stadium will be ready for the Copa del Rey final, which is scheduled for April 26, 2025.
More details on the Estadio La Cartuja redevelopment project can be seen on a separate subpage
Advertisement
Pictures
14.02.2025
14.02.2025 © Junta de Andalucía
04.02.2025
04.02.2025 © Cruz y Ortiz Arquitectos
18.11.2024
18.11.2024 © Cruz y Ortiz Arquitectos
07.11.2024
07.11.2024 © Junta de Andalucía
19.07.2024
19.07.2024 © Ayuntamiento de Santiponce 19.07.2024 © Ayuntamiento de Santiponce
Related news
2025
-
Spain: Work on Estadio La Cartuja nears completion
The Minister of Culture and Sport, Patricia del Pozo, along with the President of the Spanish Football Federation (RFEF), Rafael Louzán, recently visited the construction site of Estadio La Cartuja. The works are in the final stages ahead of the Copa del Rey final, which will take place on April 26.
-
Spain: Spanish Cup final in April, but La Cartuja is still under reconstruction
44 days - that's how many days are left until the Copa del Rey final. Meanwhile, heavy equipment is still on the pitch of Estadio La Cartuja and on the as yet unfinished stands only the first seats are being installed. However, the stadium manager assures that everything is going according to plan.