Stadion Opolski
Updated: 24.11.2024
Capacity | 11 600 |
---|---|
Country | Poland |
City | Opole |
Clubs | Odra Opole |
Category | Construction completed |
Cost | PLN 208,7 mln ($ 56 mln) |
Construction | 2021–2024 |
Design | 90 Architekci / GMT Sp. z o.o. |
Contractor | Mirbud |
Advertisement
Stadion Opolski – construction description
How did the construction of the new stadium in Opole come about?
Plans for the construction of a modern football stadium in Opole appeared even before EURO 2012 (at that time the modernization of the stadium on Oleska Street was also at stake), but the initiative took shape only in 2017, after good sporting results of Odra Opole. At the beginning of 2018, it was announced that the new stadium would be built on Północna Street, close to the Exhibition and Convention Center and Karolinka Shopping Center. A competition for the architectural concept was also launched.
How was the design for a new stadium in Opole created?
On August 14, 2018, the winning concept was selected by 90 Architekci studio in cooperation with the GMT office. The winning team was invited to produce the design documentation for the future venue. The project involves the construction of a typical football stadium, with single-level stands surrounding the pitch from all sides. A VIP zone will also be located on the stands, with the total capacity of the arena reaching 11,600 spectators. The first rows of the stands will be raised in relation to the pitch by 1.5-1.8 m. The auditorium will be entirely covered with a roof.
Inside the stadium there will be club, utility and technical areas, as well as catering and medical facilities plus conference rooms. From the outside, the stadium will be covered with a translucent, white membrane, curving into an arch, thus revealing the background. At night the facility will be able to be illuminated. Parking lots will be built next to the stadium.
What problems were encountered during the construction of the new stadium in Opole?
The rapidly growing costs of construction services and materials meant that the investment budget of PLN 100 million became unrealistic. The situation was further complicated by the COVID-19 pandemic, while the work on the project was also prolonged. On September 24, 2020, it was announced that the company had received full design documentation and a building permit. The tender for the construction of the venue was launched on December 28, 2020.
When was the tender for the new stadium in Opole finalized?
After opening the bids on July 19, 2021, it turned out that all the offers exceeded the assumed budget (PLN 180 million at the time). Thanks to the City Council's decision to increase financing, on October 4, 2021 Mirbud, which offered the lowest amount (PLN 208.7 million), was announced the winner of the tender. The investment is to be carried out by Municipal Enterprise, thanks to which the city hopes to recover VAT (the incurred expenses would then be reduced to PLN 159 million). The costs also include about PLN 4 million spent on the building plot and almost PLN 3 million on the project itself.
When did the construction of the new stadium in Opole begin?
On December 14, 2021, a contract for the construction of the facility was signed with Mirbud. Even before the end of the year the construction site was handed over to the contractor. In January 2022, geodetic work began, and in March the site was fenced. Thanks to this, it was possible for the first earthworks to start shortly after. The stadium is expected to be commissioned after less than three years, by the end of 2024. After its opening, the old stadium on Oleska Street is to be demolished and an aqua park will be built in its place.
Advertisement
Pictures
-
24.11.2024
28.10.2024
18.10.2024
26.09.2024
20.09.2024
14.08.2024
13.08.2024
12.07.2024
04.07.2024
14.06.2024
27.05.2024
16.05.2024
08.05.2024
26.04.2024
17.04.2024
12.04.2024
11.04.2024
24.03.2024
16.02.2024
10.01.2024
23.11.2023
06.11.2023
11.10.2023
11.09.2023
04.08.2023
21.07.2023
04.07.2023
19.06.2023
07.06.2023
12.05.2023
04.05.2023
18.04.2023
24.03.2023
10.03.2023
13.02.2023
16.01.2023
08.12.2022
05.11.2022
20.10.2022
05.10.2022
06.09.2022
03.09.2022
17.08.2022
01.08.2022
18.07.2022
27.06.2022
02.06.2022
13.05.2022
07.04.2022
02.04.2022
11.03.2022
Related news
2024
-
Poland: One more city says goodbye to old stadium and welcomes new one
According to the Mayor of Opole, Arkadiusz Wisniewski, the work is practically complete and construction acceptance of Odra Opole's new stadium will be carried out by the end of the year. A farewell to the old facility is also planned.
-
Poland: Opole Stadium is taking shape. What is happening?
Opole is one of the last large cities in Poland whose team still plays league matches at a stadium built before World War II. Fortunately, this will soon change, as the construction of Odra's new stadium is nearing completion.
-
Central Europe: Open day at construction site of revolutionary stadium
An open day was organised at the Polish stadium, during which those wishing to attend could see for themselves what the facility looks like from the inside. According to official information, more than 3,000 people attended the event. What is still to come at the construction site and why is the facility special?