Rostov Arena

Updated: 19.01.2018

Capacity 45 145
Country Russia
City Rostov-on-Don
Clubs FK Rostov
Category Construction completed
Tournament World Cup 2018
Construction 09/2012 - 12/2017
Cost RUB 19.4 billion
Design 2015
Contractor Crocus Group

Advertisement

Rostov Arena – construction description

This concept for Rostov-on-Don’s new stadium resulted from large cost-cutting efforts done on the initial vision for 2018 World Cup. As a result nearly nothing of the previous draft was saved, while cost still skyrocketed to overall RUB 18.5 billion at the time of this vision’s release.

The stadium is being built on the southern bank of Don, so called left bank (thus the unofficial name Stadion LevBerDon, from Russian words for Left Bank of Don). Preparatory works on site began in 2012, but progress was extremely slow as design was being worked on. Finally piling and foundation works were launched in late 2014. By mid-2015 11,044 piles were installed and half the entire concrete (92,000 cubic meters) was poured to create the superstructure.

Eventual capacity is expected to be around 45,000, of which 5,000 is to be temporary. The entire stadium, including outer wrap, multimedia screen incorporated into the façade and other facilities are expected to be ready in December 2017.

Advertisement

Pictures

17.01.2018

12.09.2017

06.08.2017

29.05.2017

13.01.2017

27.11.2016

23.09.2016

13.07.2016

10.05.2016

02.03.2016

28.01.2016

23.10.2015

27.08.2015

15.07.2015

03.06.2015

30.03.2015

03.02.2015

20.01.2015

01.12.2014

Related news

2018

2017

2016

2015