Stadion Miejski w Łodzi (Stadion ŁKS-u Łódź)
Updated: 18.05.2022
Capacity | 18 029 |
---|---|
Country | Poland |
City | Łódź |
Clubs | ŁKS |
Category | Construction completed |
Cost | PLN 94 million (phase 1), PLN 129 million (phase 2) |
Construction | 2013–2022 |
Design | Perbo-Inwestycje sp. z o.o. sp.k., DiG Sowińscy |
Contractor | Mirbud |
Address | Aleja Unii Lubelskiej 2, 94-020 Łódź |
Advertisement
Stadion ŁKS-u – construction description
How did the new ŁKS stadium happen?
In 2007 the existing ŁKS stadium was taken over by the city so that it could be comprehensively modernised. Various concepts were discussed before the final agreement was reached to build a new stadium at Unii Lubelskiej Avenue, and apart from ŁKS, Widzew was also to get a new stadium. Instead of building two smaller arenas, the possibility of building one bigger stadium used by both clubs was discussed. At the initial stage, the main reason for such a solution was the possibility of joining the bidding for the organisation of Euro 2012 matches in Łódź.
At the end of 2009 the first architectural concept contest for the new stadium at Unii Lubelskiej Avenue was held. Several impressive visions of a stadium with a capacity of about 30,000 spectators were presented, but none of them was decided to be carried out. In the summer of 2011, the city put out another tender for the construction of a new ŁKS stadium (along with a new indoor sports arena) with a minimum capacity of 15,000 spectators, under the design-and-build formula. Thanks to the construction of a new venue and a hall for more than 3,000 spectators, a modern sports complex was to be created (in the years 2006-2009, right next to the old stadium, a multipurpose indoor arena Atlas Arena was also built, which can hold more than 10,000 spectators).
Three bidders submitted offers for the tender, each of which presented its own architectural concept for the new stadium and arena. Of these, the one with the best price was the offer from the consortium of Budus SA and Mostostal Zabrze, which presented a vision of a football stadium with three roofed stands (capacity 16,500 spectators) and leaving an open space behind the northern gate, where a fourth stand could optionally be built in the future to close the structure.
Who was originally supposed to build the new ŁKS stadium?
Although Budus SA/Mostostal's bid was by far the cheapest, the amount offered (PLN 218.3 million) still exceeded the budget planned by the city (PLN 202 million). On 14th December 2011 the city councillors voted additional funds for the stadium, thanks to which on 23rd December 2011 Budus SA/Mostostal Zabrze could be declared the winner of the tender, thus rejecting the offers of Max Boegl (PLN 317.3 million) and the Hydrobudowa Polska/Remaxbud consortium (PLN 322.8 million). The contract for the construction of the stadium, the training pitch and the indoor arena, including the demolition of the old stadium, was signed on 2nd February 2012. According to the contract, the construction was to be completed by 30th December 2013 and the facility was to be fully operational by 30th April 2014.
Where was the new stadium for ŁKS Łódź built?
The new venue was to be built next to its predecessor, to the north of it (the south stand of the new facility was to be built partly on the site of the north curve of the old stadium). The plan was to demolish most of the old stadium, leaving only the eastern stand until the new arena was completed. Initially, after the contract was signed, no construction work was carried out. In May 2012, the first elements of the old stadium were dismantled in preparation for demolition. In summer 2012 a fence was erected on the construction site.
Why was the contract for the construction of the stadium at Unii Lubelskiej Avenue terminated in 2013?
However, in autumn 2012 Budus SA filed for bankruptcy, which put the completion of the project in doubt. Initially, it seemed that Mostostal Zabrze could manage the construction of the stadium on its own. In November works even started on the demolition of the northern arch of the old stadium. In the end, however, Mostostal gave up on completing the investment, agreeing to a contractual penalty of PLN 10 million. The settlement and termination of the contract took place on 25th February 2013.
What was the further development of the ŁKS stadium?
Although it was decided to continue the investment, in May the city council reduced the stadium funding for ŁKS from PLN 223 million to PLN 120 million, while allocating more funds to the construction of Widzew's new stadium. The decision may come as no surprise in the context of ŁKS' punitive relegation to the fourth division in 2013, after the club withdrew from the competition due to financial problems.
The remnant of the partnership with Budus SA/Mostostal Zabrze was the finished design for the new stadium, which was created by architects Piotr Łabowicz, Marcin Kulpam and Grzegorz Sowiński from the Perbo Group studio. Based on this design a new tender for the construction of the stadium and indoor arena was launched. Due to the budget reduction, the stadium was to have only one stand on the western side (together with extensive back-up facilities), and the construction of other stands was to be carried out in the future, according to available funds, increased demand and the return of ŁKS to professional competition.
Who became the new contractor for ŁKS stadium?
In August 2013 the tender was cancelled due to too high financial expectations of the bidders. In October 2013, when the second tender was decided, the offers were still too high, so it was decided to abandon the construction of the indoor arena in favour of the construction of the stadium itself with one stand. On 26th November 2013 a contract for the construction of the stadium was signed with Mirbud, the company that offered the best price in the second tender (94 million PLN). The contractor was given 20 months to build the first stand of the new stadium.
How did the construction of ŁKS venue proceed after signing the contract with Mirbud?
Before the end of 2013 the floodlight masts of the old stadium were dismantled. In January 2014 the western stand and the arches were demolished. Only the eastern stand, the so-called "Galera", was temporarily retained. On the partially demolished facility, which could accommodate 4994 spectators, ŁKS played its matches until the opening of the new stadium.
Unlike the previous contractor, this time the construction went smoothly, although only after six months, on 23rd June 2014, with the participation of, among others, the mayor of the city, Hanna Zdanowska, the minister of sport Andrzej Biernat, representatives of ŁKS and invited guests, the ground-breaking ceremony took place.
When was the stadium on Unii Lubelskiej Avenue in Łódź opened?
Friday 24th July 2015 marked the commissioning of the new stadium by the contractor. Already on the first weekend, open days were organised combined with, among other things, a tour of the new stand. However, the official opening took place on 2nd August 2015 with a friendly match between ŁKS and Pogoń Lwów (2:1). The newly opened western stand had 5,716 capacity for spectators. Along with it, extensive sports and administrative facilities were also built. The new venue was managed by the Municipal Arena of Culture and Sports (MAKiS). After the opening, the demolition of the old stadium was completed, and parking spaces were subsequently created in its place.
When was the indoor sports arena next to the ŁKS stadium built?
Between 2016 and 2018, a new sports hall capable of holding over 3,000 spectators was built right next to the stadium (Łódź Sport Arena im. Józefa Żylińskiego). This arena was originally intended to be built together with the stadium, but then its construction was abandoned for cost-saving reasons. In the same period as the new hall, a training centre for ŁKS football players was built at Minerska Street.
What changes took place at ŁKS stadium before the second phase of construction?
At the beginning of 2019, temporary floodlight masts were erected behind the eastern edge of the pitch, which, together with lamps placed in the roof of the western stand, created illumination of the pitch; a sector for fans of visiting teams was also created behind the northern gate, accommodating 292 fans. In the same year, ŁKS returned to the Ekstraklasa. In autumn 2019, the field heating system was put into operation.
When was the contract for phase II of the ŁKS stadium construction signed?
On 28th August 2018, the tender for the construction of the three missing stands at ŁKS stadium was announced. In November 2018, due to too expensive bids, the tender was cancelled. After a technical consultation with the bidders, a new tender was launched on 1st February 2019. And this time the offers exceeded the assumed budget, but thanks to the increase in funding from the city, it was possible to choose the contractor. The offer from Mirbud, proposing to complete the construction of the arena for PLN 129 million, won (it was the same contractor who carried out the phase I of the construction). The contract was signed on 5th June 2019, with a deadline of 36 months to complete the facility.
How did the phase II of construction of the ŁKS Łódź stadium proceed?
Again, the works proceeded very smoothly, the more so because Mirbud at the start already had a building permit for two of the three stands to be constructed. The contractor declared the commissioning ahead of schedule, and the progress was not significantly slowed down by the COVID-19 pandemic either. A change from the initial plans was the redesigning of the stand behind the northern gate, which was equipped with additional office facilities. While the works were ongoing, the facility was fully functional and ŁKS were able to play their matches there. In the summer of 2021, the stadium was officially named after Władysław Król.
When were all the stands of the new ŁKS stadium opened?
The opening of the arena after the commissioning of all four stands took place on 22nd April 2022. The ceremony included a concert by Margaret, a presentation of all sections of ŁKS as well as partner clubs and football academy teams, and the awarding of badges to deserving ŁKS athletes. At 8.30 p.m. a match of the 29th round of I league was played, in which the hosts faced Chrobry Głogów (0:1).
Is the ŁKS stadium the only stadium investment in Łódź?
The facility is one of three major stadium investments that were initiated in Łódź in the second decade of the 21st century, alongside the new Widzew stadium (2015-2017) and the speedway stadium (2016-2018).
Advertisement
Pictures
-
14.04.2022
08.04.2022
28.03.2022
18.02.2022
26.01.2022
29.12.2021
08.12.2021
25.11.2021
20.09.2021
16.08.2021
09.07.2021
30.04.2021
21.04.2021
28.03.2021
23.03.2021
29.01.2021
30.12.2020
18.12.2020
20.11.2020
16.11.2020
21.10.2020
07.10.2020
21.09.2020
03.09.2020
19.07.2020
15.06.2020
27.05.2020
01.05.2020
09.04.2020
12.03.2020
13.02.2020
17.01.2020
18.12.2019
26.11.2019
07.11.2019
31.10.2019
22.10.2019
19.09.2019
25.07.2015
10.07.2015
10.06.2015
21.05.2015
02.05.2015
07.04.2015
17.03.2015
28.02.2015
07.02.2015
08.01.2015
16.12.2014
19.11.2014
16.10.2014
26.07.2014
23.06.2014
17.02.2014
03.01.2014
Related news
2021
2020
-
Poland: Fourth stand in Łódź under construction
Construction of the fourth and last grandstand began in Łódź, at the ŁKS stadium. The contractor has also confirmed being a few months ahead of schedule, expecting to finish the whole project early.
-
Poland: ŁKS stadium should be ready 6 months ahead of schedule
The third major municipal stadium in Łódź is now a year under construction. Its delivery date has been set for mid-2022 but the general contractor has just confirmed the project should be done half a year earlier.
2019
2018
-
Poland: Tender launched for ŁKS stadium
Companies from across Europe have until early October to give their offers on design+build project of the new ŁKS stadium in Łódź. Three new grandstands will raise capacity to over 20,000 covered seats.
-
Poland: Łódź provides more detail about third stadium
Third largest Polish city isn't stopping with two modern stadiums. Third and largest one is expected to open in 2020 or 2021, depending on progress. We now know what it's about to host aside from football.
2017
-
Poland: Expansion of ŁKS stadium to end in 2020
Next year's budget of Łódź is almost approved, pending just one more change. That change covers commencement of works on the expansion of ŁKS stadium to reach around 20,000 seats.
-
Poland: Three stands announced for ŁKS
They will raise capacity by 12,000 or even 14,000 people. A lot for a third league club, right? But this stadium's history was always supposed to end that way.
2015
-
Poland: New stadium in Lodz delivered on time
Poland’s third largest city is no longer a blank spot on the map of modern stadiums. First of three (!) new arenas was handed over on Friday and now awaits opening game.
-
Poland: One more farewell to iconic stadium in Poland
It saw a fair number of great games, including Poland’s wins over Turkey, USA, Norway or Hungary. Yesterday fans filled it to capacity, saying goodbye to the last standing terrace.
2014
-
Poland: Uphill journey of ŁKS
Two-time domestic champions, one of Poland's oldest football clubs, ŁKS folded last year after insolvency. Now supporters are rebuilding it from scratch and have just filed a stadium capacity expansion application.
-
New construction: Stadion ŁKS-u Łódź
Current images are rather sad and sentimental as the old stadium, one of Poland’s most well known, is being demolished. Soon it will be replaced by training pitches, while a brand new ground is to be built north of the site, initially with only one stand.