Stadion Hristo Botev
Updated: 06.07.2024
Target capacity | 18 788 |
---|---|
Country | Bulgaria |
City | Plovdiv |
Clubs | Botev Plovdiv |
Category | Construction in progress |
Construction | 2012–? |
Cost | 43.6 mln BGN (29 mln $) |
Design | Vamos Architecture & Design |
Contractor | PIMK, Valmex |
Design time | 2012–2014 |
Advertisement
Stadion Hristo Botev – construction description
First conceptual renditions of this stadium were presented back in 2012. But with the club not having the 35-year ownership of the ground secured back then (only approved in Feb 2014) and final design being worked on, the progress was symbolic at first.
Real demolition of the old stands began in early 2014 as the club presented its final vision of Bulgaria’s best stadium, or so it was called upon presentation. After the late launch construction was announced to be done in April 2015, with opening scheduled for May.
The modified design by local office Vamos includes 75% of the 18,788 seats covered by enclosed roof (initial vision had uncovered corners) with all spectators located on one tier. Dominated by yellow and black colours of the club, the stands will have a typical layout: north end will belong to the fanatic fans, signaled by the big number 12 (for ‘12th man’) written with seats. Away fans will have 1,500-1,600 seats in the south.
The new stadium will retain only one element of the old one – historical stairs leading to the main grandstand. Even the name will be changed, but this is expected to be preceded by thorough consultation.
The investment was able to get off the ground thanks to private funding from the club's owner, Tsvetan Vasilyev, one of the richest men in Bulgaria. For the duration of the project, Botev moved to a training stadium at his football academy, also built with funds from the billionaire.
In the summer of 2014, however, work was halted as Tsvetan Vasilyev was arrested and his bank closed. The city authorities tried to rescue the situation by allocating some funds to continue the work, but in 2015 the construction was definitely stopped. By this time the reinforced concrete structure of the eastern and southern stands was ready, as well as part of the skeleton in the north. The least amount of work was done on the west side.
Work resumed in 2019, but at that time it was mainly limited to the removal of trees and bushes that had grown on the site of the halted construction. It was not until the end of 2020, thanks to a transfer of 25 million leva from the central budget, that work began to finalize the project. The contractor was given two years to complete the construction, although the stadium was finally able to be inaugurated on April 29, 2023.
Work continues after the opening, with the finishing of the roof over the east stand underway in the summer of 2023 and placing the roof over the stands behind the goals starting in September 2023.
Advertisement
Pictures
-
06.07.2024
08.05.2024
14.04.2024
01.04.2024
30.03.2024
24.03.2024
08.03.2024
11.02.2024
02.02.2024
18.01.2024
09.12.2023
01.12.2023
10.11.2023
27.10.2023
13.10.2023
03.10.2023
02.10.2023
14.09.2023
11.08.2023
14.04.2023
07.04.2023
31.03.2023
30.03.2023
26.03.2023
12.03.2023
17.02.2023
09.02.2023
22.12.2022
07.12.2022
25.11.2022
28.10.2022
14.10.2022
19.09.2022
09.09.2022
18.08.2022
10.08.2022
26.07.2022
06.07.2022
18.06.2022
07.06.2022
31.05.2022
13.04.2022
12.03.2022
19.02.2022
13.02.2022
23.12.2021
21.11.2021
15.09.2021
30.07.2021
15.06.2021
17.05.2021
20.04.2021
02.04.2021
06.03.2021
10.02.2021
01.02.2021
22.01.2021
08.01.2021
28.12.2020
14.12.2020
04.11.2019
09.03.2019
11.01.2017
08.10.2016
18.02.2015
08.01.2015
29.11.2014
02.11.2014
24.09.2014
08.08.2014
01.06.2014
04.05.2014
23.03.2014
18.02.2014
18.01.2014
04.01.2014
18.12.2013
14.07.2013
Related news
2024
2020
-
Bulgaria: Work resumes in Plovdiv, stadium to come in 2022
After nearly 5 years without any progress, construction work has finally restarted on the site of Stadion Hristo Botev in Plovdiv. New contractors have pledged to finish in exactly 2 years.
-
Bulgaria: Botev stadium contractor in a month
The project is already 5 years late and will likely exceed a 7-year delay in the end. That's because we're still a month before contractor is selected and he will need 2 years to finish what has been abandoned since 2015.
-
Bulgaria: Finally, a breakthrough for Botev?
Bulgarian prime minister announced that he himself will supervise the construction of Botev Plovdiv's new stadium. Will the curse finally be taken off the unfinished stadium?
2019
2014
-
Bulgaria: Construction resumes in Plovdiv, but trouble not gone
After the owner and main investor was arrested, all construction work seized at Stadion Hristo Botev. Now works are resumed, but completion is still at risk, according to insideworldfootball.com.
-
New construction: Stadion Hristo Botev
We've already shown you the design, now it's time for construction updates. Thanks to the courtesy of grassroots Botev profile at facebook we'll provide you with regular progress photos from now on.