Stadion Georgi Asparuhov (Gerena)

Updated: 29.03.2016

Capacity28 000
Country Bulgaria
CitySofia
ClubsLevski
CategoryConstruction completed
Construction 2013 - ?
Design time 2012
Contractor Glavbolgarstroi

Advertisement

Stadion Georgi Asparuhov – construction description

The stadium is to be built in three phases. First the west and south stands are to be rebuilt until May 2014. Then eastern stand goes through similar works (until 2015) and last one to be rebuilt anew is the northern curve – should be ready in 2017.

Capacity was announced to stand at 28,000 people, making the venue similar in size to its predecessor. Skyboxes are to be found on both sides of the pitch, with ends being left for regular fans only. Not all sections of the crowd are to be covered – corner stands and first rows of each stand will have no roof.

Between 2013 and 2016, the western part of the stadium was rebuilt with a new main stand, but without the planned roof and facade. Further work is currently not being carried out due to lack of funding.

Advertisement

Pictures

    

28.03.2016

26.02.2016

09.12.2015

30.10.2015

05.09.2015

21.07.2015

16.06.2015

03.05.2015

22.03.2015

03.11.2014

19.09.2014

11.08.2014

05.07.2014

07.06.2014

17.04.2014

12.03.2014

23.01.2014

12.12.2013

10.11.2013

13.10.2013

14.09.2013

03.08.2013

04.07.2013

21.03.2013

28.02.2013

05.02.2013

Related news

2021

2013