Malatya Arena

Updated: 18.05.2017

Capacity25 000
Country Turkey
CityMalatya
ClubsMalatyaspor
CategoryConstruction completed
Construction 2013-2016
Cost TRY 75 million
Design Azaksu Mimarlik

Advertisement

Malatya Arena – construction description

Initial bids to build a new stadium in Malatya date back to 2007, but it wasn't until 2011 that an early design was drawn, based on which the project took off.

Contractor was initially selected back in 2011, but construction only began in 2013, expected to last over one year. Unfortunately after delays the contractor abandoned his work site in 2015 and new one arrived in early 2016 to complete the work.

The 25,000-seater will have parts of its lower stands based on land slopes, while other sections will see infrastructure underneath, like offices or garages. This allows to keep the budget low.

At the same time architects from the Azaksu practice managed to include in the calm and simple outer shape a distinctive feature. Behind one goal the cladding will split into two layers, with one creating a shaded plaza in front of the stadium.

Advertisement

Pictures

    

18.05.2017

20.03.2017

07.02.2017

04.01.2017

26.11.2016

26.09.2016

22.08.2016

30.06.2016

14.05.2016

16.04.2016

20.07.2015

18.04.2015

03.03.2015

20.01.2015

15.12.2014

17.09.2014

14.07.2014

09.06.2014

05.04.2014

04.02.2014

02.01.2014

01.12.2013

14.10.2013

24.08.2013

25.07.2013

01.05.2013

30.03.2013

05.02.2013