ORLEN Stadion

Updated: 26.07.2023

Capacity15 000
Country Poland
CityPłock
ClubsWisła
CategoryConstruction completed
Cost PLN 166.5 mln ($ 44 mln)
Construction 2020 - 29/11/2022
Design Perbo-Inwestycje
Contractor Mirbud SA

Advertisement

ORLEN Stadion – construction description

The new stadium in Płock is being delivered as a design+build project, which means contract signing on Nov 29, 2019, was not equal to groundbreaking. Rather, for most of the first year, design work was scheduled to take place, thankfully not significantly impacted by COVID-19 issues. Demolition of first parts of the old stadium was moved to second half of 2020.

Once the 2019/20 Ekstraklasa season concluded, demolition of the east 'crescent' began, soon followed by dismantling of the north-western away section. Only part of the main stand, the field, floodlights and pavilion behind the south goal were left in order to ensure games can be played. This way construction can be phased without Wisła Płock being forced to relocate. As a result, the contract is longer than for regular construction, spanning 3 years.

Based loosely on the initial municipal concept by Bończa Studio, the vision prepared by Mirbud in the 'design+build' tender. It also foresees a stadium with a single, continuous tier of seating for some 15,000 people. The front row is elevated, awarding everyone a better overview of the field.

What sets the stadium apart from others is the creative use of blinds as outer cladding. They're horizontal on the west facade, vertical on the east and transitioning from one to the other behind goals. Thanks to this openwork form the stadium is naturally ventilated, while also offering some protection from the elements both inside and on the concourses.

Outer promenade around the stadium is accessible from ground level in the south, but requires the use of stairs in the north, owing this difference to natural land slope. But bulk of fans are expected to use the southern access, where a large plaza is planned.

The west side is the only grandstand to have extensive facilities attached, spread across 4 levels. These include two levels of hospitality – a large and semi-open business club and several private boxes above. On top of these rooms there's place for commentators boxes and command center for safety and security authorities.

Advertisement

Pictures

26.07.2023

20.06.2023

21.05.2023

07.05.2023

10.04.2023

15.03.2023

22.02.2023

28.01.2023

06.01.2023

23.12.2022

03.12.2022

17.11.2022

27.10.2022

12.10.2022

23.09.2022

07.09.2022

24.08.2022

10.08.2022

03.08.2022

28.07.2022

21.07.2022

17.07.2022

15.07.2022

06.07.2022

30.06.2022

23.06.2022

16.06.2022

09.06.2022

03.06.2022

19.05.2022

05.05.2022

30.04.2022

23.04.2022

12.04.2022

28.03.2022

12.03.2022

12.02.2022

26.01.2022

01.01.2022

18.12.2021

24.11.2021

07.11.2021

19.10.2021

05.10.2021

25.09.2021

07.09.2021

31.07.2021

11.07.2021

11.06.2021

20.05.2021

11.05.2021

01.05.2021

27.04.2021

12.04.2021

08.04.2021

31.03.2021

22.03.2021

08.03.2021

02.03.2021

21.02.2021

06.02.2021

31.01.2021

22.01.2021

17.01.2021

05.01.2021

27.12.2020

20.12.2020

12.12.2020

13.11.2020

25.10.2020

23.09.2020

28.08.2020

12.08.2020

Related news

2021

2020