Italy: Time is running out, work is progressing. What is currently happening at Fiorentina stadium? Time is running out, but progress is accelerating. At Stadio Artemio Franchi, the first visible results of the redevelopment are already taking shape — the new Curva Fiesole is rising, while foundations for the future roof are being prepared, set to transform the stadium entirely.

Advertisement

Biggest progress at Stadio Artemio Franchi? Curva Fiesole

The most visible progress is currently taking place in the Curva Fiesole sector, the stand occupied by the most passionate supporters of ACF Fiorentina. The installation of the first prefabricated steps has begun, which will ultimately form the new structure of the seating area. These elements are being mounted on previously prepared support beams that form the foundation of the entire structure.

The construction process has been planned in stages. For now, the lower part of the stand, closest to the pitch, remains free. This is due to the need to ensure access for heavy equipment, including cranes. Only after the work in the upper sections is completed will it be possible to finish the lower rows and extend the stand directly to the edge of the field.

At the same time, intensive work is underway on the foundations for the roof structure. Around the stadium, specialized ground works are being carried out, including the installation of micropiles and the preparation of bases for future load-bearing pillars. The new roof will cover not only Curva Fiesole but also other parts of the stadium, including the main stand and the Maratona sector. This is one of the key elements of the modernization, significantly improving spectator comfort and allowing events to be held regardless of weather conditions.

Timeline of the Artemio Franchi modernization and the race against time

City authorities emphasize that the modernization of Stadio Artemio Franchi is proceeding in line with the planned schedule, with completion set for October 2026. However, some local politicians point to discrepancies between the originally announced timeline and the actual start of the stand assembly.

Critics highlight a delay of several months compared to earlier assumptions, suggesting possible setbacks for the entire project. City officials reject these claims, explaining that the dates in the schedule referred to the start of the production of structural elements, not their installation at the stadium. In their view, the current stage of work confirms that the project remains on track.

Future capacity and functionality of Artemio Franchi

While the main goal of the investment is to improve infrastructure quality, optimizing the layout of the seating and the stadium’s functionality is also important. The new Curva Fiesole will offer better visibility and a steeper stand design, which should translate into a more intense fan experience.

The modernization of Stadio Artemio Franchi is also intended to increase its attractiveness as a multifunctional venue capable of hosting a variety of sports and cultural events. As a result, the stadium is expected to remain a key part of Florence’s urban infrastructure for many years to come.